A contractor's insurance policy has a $2 million per occurrence limit with a $5 million aggregate limit. Three separate incidents occur with damages of $1.8 million, $1.2 million, and $2.5 million respectively. How much will the insurance company pay in total?
Correct Answer
B) $5.0 million
Per occurrence payments: $1.8M + $1.2M + $2.0M (limited) = $5.0M, which equals the aggregate limit.
Why This Is the Correct Answer
Option B ($5.0 million) is correct. Each claim is capped at the $2M per-occurrence limit, then the aggregate acts as a second ceiling. Incident 1: $1.8M paid in full (under $2M limit). Incident 2: $1.2M paid in full (under $2M limit). Running total: $3.0M. Incident 3: $2.5M would be limited to $2.0M per-occurrence, but only $2.0M remains under the $5M aggregate, so exactly $2.0M is paid. Total: $1.8M + $1.2M + $2.0M = $5.0M, which equals the aggregate limit.
Why the Other Options Are Wrong
Option A: $3.0 million
$3.0 million is incorrect. This would only account for the first two incidents ($1.8M + $1.2M) and ignore the third incident entirely, or it represents the first incident capped incorrectly. The aggregate has not yet been exhausted after two incidents.
Option C: $5.5 million
$5.5 million is incorrect. This adds all three incidents at face value ($1.8M + $1.2M + $2.5M = $5.5M) without applying either the per-occurrence limit to the third incident or the $5M aggregate cap. Both limits must be applied.
Option D: $4.5 million
$4.5 million is incorrect. This may result from incorrectly limiting the third incident to the per-occurrence cap ($2.0M) but then miscalculating the total ($1.8 + $1.2 + $1.5 = $4.5M), or from some other error. The aggregate cap of $5M governs the final answer.
Memory Technique
Think of the per-occurrence limit as a 'bucket' per incident and the aggregate as the 'tank' that holds all buckets. Each bucket can hold at most $2M. The tank holds at most $5M total. Fill each bucket (up to $2M), pour into the tank, stop when the tank is full.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
What is the primary purpose of a performance bond on a construction project?
Next Question
A mechanical subcontractor's work causes water damage to completed electrical work. The subcontract includes a mutual indemnification clause. Who is primarily responsible for the cost of repairs?
