A contractor's general liability policy has a $500,000 per occurrence limit and $1,000,000 aggregate limit. After two claims totaling $300,000 and $400,000, how much coverage remains for additional claims?
Correct Answer
A) $300,000
The aggregate limit is reduced by total claims: $1,000,000 - $300,000 - $400,000 = $300,000 remaining.
Why This Is the Correct Answer
The aggregate limit is the total the insurer will pay for all claims during the policy period. Two claims of $300,000 and $400,000 total $700,000 paid against the $1,000,000 aggregate. The remaining coverage is $1,000,000 - $700,000 = $300,000.
Why the Other Options Are Wrong
Option B: $700,000
$700,000 is the total already paid out in claims β not the remaining coverage. Confusing the amount paid with the amount remaining is a classic calculation error.
Option C: $0
$0 would be correct only if the aggregate limit had been fully exhausted. Since only $700,000 of the $1,000,000 aggregate has been used, $300,000 of coverage still remains.
Option D: $500,000
$500,000 is the per-occurrence limit, not the remaining aggregate. Per-occurrence limits cap individual claim payouts but do not represent remaining aggregate capacity after prior claims.
Memory Technique
Think of the aggregate as a bucket with $1,000,000. Each claim scoops water out. After scooping $300K and $400K ($700K total), only $300K of water remains in the bucket.
More Hawaii Questions
What is the minimum general liability insurance coverage required for Hawaii contractors under HRS 444?
A contractor's license expires on June 30th. What is the late renewal penalty fee in Hawaii?
A contractor completes $85,000 worth of work on a residential project in Hawaii. The property owner fails to pay. Under HRS 507, what is the maximum lien amount the contractor can claim?
A contractor's insurance policy has a $1 million aggregate limit and a $500,000 per occurrence limit. Two separate incidents occur: one causing $400,000 in damages and another causing $300,000. How much will the insurance cover?
Under Hawaii's mechanics lien law, a subcontractor must provide preliminary notice within how many days of first furnishing labor or materials?
A subcontractor provides $28,000 worth of plumbing work but is not paid by the general contractor. Under HRS 507, what is the priority of the mechanics lien compared to a mortgage recorded before construction began?
A contractor discovers contaminated soil during excavation of a residential property. Under Hawaii environmental regulations, who must be notified immediately?
A contractor working on a project in a Hawaii historic district must obtain approval from which entity before beginning work?
A contractor fails to obtain required building permits before starting work. The property owner discovers this and terminates the contract. Under Hawaii law, what is the contractor's right to payment?
A contractor has 12 employees with a total annual payroll of $480,000. If the workers compensation rate is $12.75 per $100 of payroll, what is the annual premium?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A subcontractor provides $28,000 worth of plumbing work but is not paid by the general contractor. Under HRS 507, what is the priority of the mechanics lien compared to a mortgage recorded before construction began?
Next Question
A contractor fails to obtain required building permits before starting work on a residential addition. What is the most likely consequence under Hawaii building codes?