EstatePass
NASCLAPlans & Specsmedium10% of exam part

A contractor receives shop drawings for structural steel 45 days after submitting them. The contract allows 30 days for review. What is the most appropriate action?

Correct Answer

A) Request a time extension for the delay

The 15-day delay in shop drawing review may impact the project schedule, so requesting a time extension is appropriate to document the delay and adjust the schedule accordingly.

Answer Options
A
Request a time extension for the delay
B
Proceed with fabrication immediately
C
File a claim for delay damages
D
Reject the shop drawings as untimely

Why This Is the Correct Answer

The 15-day overrun in the review period may have caused a ripple delay in the project schedule. Requesting a time extension formally documents the delay, preserves the contractor's rights, and adjusts the contract completion date. This is the prudent, contractually protective first step.

Why the Other Options Are Wrong

Option B: Proceed with fabrication immediately

Proceeding with fabrication without addressing the schedule impact ignores the fact that the late return may have already shifted other activities. Fabricating immediately also risks compounding problems if the reviewed drawings contain changes.

Option C: File a claim for delay damages

Filing a claim for delay damages is premature. A time extension should be sought first; monetary claims require proof of actual cost impact and are typically pursued after exhausting other remedies. Jumping straight to a damages claim is aggressive and may violate the contract's dispute-resolution sequence.

Option D: Reject the shop drawings as untimely

Rejecting shop drawings as untimely has no contractual basis β€” the drawings have already been reviewed and returned. The remedy for a late review is a schedule adjustment, not rejection of the submittal.

Memory Technique

Late review = Time first, Money later. Lock in the time extension while the delay is fresh; delay damages require more documentation and come in a later step.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.