EstatePass
la-supplementLouisiana State Supplementmedium

A contractor receives a stop payment notice on a project with a contract value of $450,000. The contractor must withhold what amount from payments to the subcontractor?

Correct Answer

C) The lesser of the amount claimed or amount owed

Under Louisiana law, upon receiving a stop payment notice, the contractor must withhold the lesser of the amount claimed in the notice or the amount currently owed to the subcontractor.

Answer Options
A
110% of the amount claimed
B
10% of the total contract value
C
The lesser of the amount claimed or amount owed
D
The full amount claimed in the notice

Why This Is the Correct Answer

Under Louisiana law, when a contractor receives a stop payment notice, the contractor must withhold the lesser of (1) the amount claimed in the notice or (2) the amount currently owed to the subcontractor. This prevents the contractor from being required to withhold more than they actually owe the subcontractor, which would be unjust.

Why the Other Options Are Wrong

Option A: 110% of the amount claimed

110% of the amount claimed is a rule that appears in some other states' lien laws to provide a cushion for the claimant. Louisiana does not use a 110% multiplier for stop payment notice withholding.

Option B: 10% of the total contract value

10% of the total contract value ($45,000) is not the withholding rule. The total contract value is irrelevant to the withholding calculation; only the amount claimed and amount owed to the sub matter.

Option D: The full amount claimed in the notice

Withholding the full amount claimed sounds protective but could exceed what is actually owed to the subcontractor. Louisiana law uses the 'lesser of' formula to keep withholding fair and proportional.

Memory Technique

Stop notice = stop at the lesser amount. Imagine a stop sign: you cannot go past what you actually owe. Lesser = safer for everyone. 'Lesser of claimed or owed' = Louisiana stop payment rule.

Was this explanation helpful?

More la-supplement Questions

A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?

A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?

A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?

Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?

A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?

Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?

Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?

A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?

A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?

A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.