A contractor receives a Notice of Intent to Lien for $15,000. They dispute the amount and believe only $8,000 is owed. Under Michigan law, what should the contractor do to protect their interests?
Correct Answer
D) Respond in writing within the required timeframe
The contractor should respond in writing within the required timeframe to dispute the lien amount and protect their legal position under Michigan's Construction Lien Act.
Why This Is the Correct Answer
Under Michigan's Construction Lien Act, when a contractor receives a Notice of Intent to Lien and disputes the amount, the proper protective action is to respond in writing within the required statutory timeframe. This formal response preserves the contractor's legal position and documents the dispute.
Why the Other Options Are Wrong
Option A: File a counter-lien
A 'counter-lien' is not a recognized legal mechanism in Michigan's Construction Lien Act for this scenario. Contractors do not respond to lien notices by filing counter-liens β that concept does not exist in this context.
Option B: Pay the full $15,000 under protest
Paying the full disputed amount under protest does not protect the contractor's interests and would likely be seen as acceptance of the $15,000 claim. It also unnecessarily pays $7,000 more than the contractor believes is owed.
Option C: Ignore the notice since they dispute the amount
Ignoring a Notice of Intent to Lien is one of the worst actions a contractor can take. Failure to respond can result in a valid lien being filed and could complicate the contractor's ability to challenge the amount later.
Memory Technique
When in doubt, respond in writing and on time. Think 'WWT' β Write Within Time. For any lien dispute in Michigan, a timely written response is your shield. Silence = consent in lien law.
More Michigan Questions
A Michigan contractor forms an S-Corporation. What is the maximum number of shareholders allowed?
A contractor's employee is injured on a job site in Michigan. The contractor's workers' compensation insurance has a $500 deductible per claim. The total medical costs are $12,500 and lost wages are $3,200. What is the contractor's out-of-pocket cost for this claim?
What is the minimum general liability insurance coverage amount required for Michigan residential builders?
Under Michigan Act 299, what is the consequence for a contractor who performs work outside the scope of their license classification?
A contractor discovers that a subcontractor has filed a construction lien against their project. The general contractor believes the lien is invalid. What is the primary legal mechanism to challenge the lien in Michigan?
Under Michigan Act 299, what happens if a contractor continues to work without a valid license after it expires?
Which of the following best describes the 'pay when paid' clause limitation under Michigan law?
A project has total costs of $180,000 including $75,000 labor and $105,000 materials. With workers compensation at 7.8% of labor costs and general liability at 0.4% of total costs, what are the combined insurance costs?
A Michigan contractor is forming an LLC. What is the minimum general liability insurance coverage required for residential builders under Michigan law?
Under Michigan Act 299, a contractor's license must be renewed every:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A Michigan contractor forms an S-Corporation. What is the maximum number of shareholders allowed?
Next Question
A Michigan contractor discovers their employee was injured on the job but failed to report it immediately. What is the maximum penalty under Michigan workers' compensation law for late reporting?