A contractor receives a citation with a proposed $3,500 penalty. Within how many days must they respond to contest the citation?
Correct Answer
B) 15 days
B&P Code Section 7099.2 requires that citations be contested within 15 days of service to preserve appeal rights.
Why This Is the Correct Answer
Under B&P Code Section 7099.2, a contractor must respond to contest a citation within 15 days of service. Failing to respond within this window causes the citation and penalty to become final and non-appealable.
Why the Other Options Are Wrong
Option A: 30 days
30 days is the deadline to request a formal hearing after contesting, not the initial response deadline to contest the citation itself. This is a common mix-up on the exam.
Option C: 20 days
20 days is not a deadline found in Section 7099.2. It is a distractor that falls between 15 and 30 days.
Option D: 10 days
10 days is too short and is not the period specified for contesting citations under B&P Code Section 7099.2.
Memory Technique
15 days to say 'I contest!' β think of a boxing match: you have 15 rounds to fight back. After 15 days, the bell rings and the citation is final.
More California Questions
A Class C-10 electrical contractor has annual gross receipts of $3.2 million. What is the required bond amount under current California law?
Under B&P Code Section 7125.4, what is the fee for initial Home Improvement Salesperson registration?
According to B&P Code Section 7125, what is the maximum penalty the CSLB can impose for contracting without a license?
A home improvement contract for $8,500 requires a 3-day right to cancel notice. The contract is signed on Tuesday at 2 PM. When does the cancellation period expire?
A contractor employs 15 workers across multiple job sites. The total annual payroll is $850,000 with a workers' comp rate of 4.1%. If they self-insure with a deposit requirement of 125% of estimated annual premium, what deposit is required?
A C-10 electrical contractor wants to perform plumbing work valued at $8,000 as part of a larger electrical project. Is this permissible under CSLB regulations?
A homeowner discovers that an unlicensed contractor performed $25,000 worth of work on their property. Under B&P Code Section 7031, what remedy is available to the homeowner?
A Class B general building contractor wants to perform electrical work valued at $750. According to the B&P Code, this contractor:
A contractor's qualifying individual leaves the company. How many days does the contractor have to replace them before the license becomes invalid?
According to B&P Code Section 7031, what happens to a contractor's right to payment if they perform work while unlicensed?