A contractor receives a citation with a $2,000 civil penalty for failing to obtain permits. The contractor wants to contest it. Within how many days must they request a hearing?
Correct Answer
C) 30 days
B&P Code Section 7099.2 requires that requests for hearings on citations must be made within 30 days of service of the citation.
Why This Is the Correct Answer
B&P Code Section 7099.2 requires that a contractor who wishes to contest a CSLB citation must submit a written request for a hearing within 30 days of service of the citation. Failure to request a hearing within this window makes the citation and penalty final.
Why the Other Options Are Wrong
Option A: 20 days
20 days is not the statutory deadline for requesting a hearing on a CSLB citation. This number does not appear in B&P Code Section 7099.2 and may be confused with other administrative deadlines in unrelated contexts.
Option B: 15 days
15 days is too short and is not the correct period under B&P Code Section 7099.2. This figure may be confused with shorter notice periods found in other parts of contractor law.
Option D: 45 days
45 days exceeds the statutory deadline. Waiting 45 days would cause the contractor to miss the 30-day window, making the citation final and enforceable without a hearing.
Memory Technique
Think '30 days to fight, or lose the right.' The number 30 also matches a month β imagine you have one full month on the calendar to act before the citation becomes permanent.
More California Questions
A Class C-10 electrical contractor has annual gross receipts of $3.2 million. What is the required bond amount under current California law?
Under B&P Code Section 7125.4, what is the fee for initial Home Improvement Salesperson registration?
According to B&P Code Section 7125, what is the maximum penalty the CSLB can impose for contracting without a license?
A home improvement contract for $8,500 requires a 3-day right to cancel notice. The contract is signed on Tuesday at 2 PM. When does the cancellation period expire?
A contractor employs 15 workers across multiple job sites. The total annual payroll is $850,000 with a workers' comp rate of 4.1%. If they self-insure with a deposit requirement of 125% of estimated annual premium, what deposit is required?
A C-10 electrical contractor wants to perform plumbing work valued at $8,000 as part of a larger electrical project. Is this permissible under CSLB regulations?
A homeowner discovers that an unlicensed contractor performed $25,000 worth of work on their property. Under B&P Code Section 7031, what remedy is available to the homeowner?
A Class B general building contractor wants to perform electrical work valued at $750. According to the B&P Code, this contractor:
A contractor's qualifying individual leaves the company. How many days does the contractor have to replace them before the license becomes invalid?
According to B&P Code Section 7031, what happens to a contractor's right to payment if they perform work while unlicensed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor employs 8 workers and has an annual payroll of $450,000. The workers' compensation insurance premium rate is 3.2% of payroll. What is the annual premium cost?
Next Question
A general contractor subcontracts plumbing work to an unlicensed individual. The general contractor may face: