EstatePass
Contract AdminContractsmedium40% of exam part

A contractor receives a $500,000 progress payment with 10% retainage held. If the contractor's overhead and profit margin is 15% and material costs for this billing period were $200,000, what is the total amount of retainage being held?

Correct Answer

C) $55,556

The total work completed is $500,000 ÷ 0.90 = $555,556. The retainage held is 10% of the total work completed: $555,556 × 0.10 = $55,556.

Answer Options
A
$45,000
B
$50,000
C
$55,556
D
$57,500

Why This Is the Correct Answer

Option B is correct because retainage is calculated on the total work completed, not just the payment received. Since the contractor received $500,000 after 10% retainage was held, this represents 90% of the total work value. To find the total work completed, we divide $500,000 by 0.90 to get $555,556. The retainage held is then 10% of this total amount, which equals $55,556.

Why the Other Options Are Wrong

Option B: $50,000

This incorrectly attempts to factor in the 15% overhead and profit margin, which is irrelevant to retainage calculations. Retainage is calculated on the total contract value regardless of the contractor's markup structure.

Option D: $57,500

This appears to calculate retainage on some arbitrary reduced amount, possibly confusing material costs or other factors. It doesn't follow the proper retainage calculation methodology of finding the total work value first.

Memory Technique

Remember 'BIRD' - Backwards calculation, Identify total work, Retainage on total, Disregard markup percentages. Always divide the net payment by the percentage actually paid to find the gross amount first.

Reference Hint

Florida Building Construction Standards - Chapter on Progress Payments and Retainage, or Florida Statutes Chapter 713 regarding construction liens and payment procedures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.