A contractor performs $45,000 of electrical work requiring a 15% retention. If the retention is released after final inspection, what amount was held during construction?

Correct Answer

D) $6,750

$45,000 × 0.15 = $6,750 held as retention during construction until final inspection approval.

Answer Options
A
$6,250
B
$5,750
C
$7,250
D
$6,750

Why This Is the Correct Answer

$45,000 × 0.15 = $6,750 held as retention during construction until final inspection approval.

Was this explanation helpful?

More al-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.