A contractor completed work on March 1st but the property owner refuses to pay the $28,000 invoice. In Alabama, what is the deadline to file a mechanics lien?

Correct Answer

A) June 29th (120 days)

Alabama lien law requires mechanics liens to be filed within 120 days of completion of work or last furnishing of materials.

Answer Options
A
June 29th (120 days)
B
August 28th (180 days)
C
February 28th of the following year (365 days)
D
May 30th (90 days)

Why This Is the Correct Answer

Alabama lien law requires mechanics liens to be filed within 120 days of completion of work or last furnishing of materials.

Was this explanation helpful?

More al-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.