EstatePass
AlabamaAL Supplementmedium100% of exam part

A contractor completed work on March 1st but the property owner refuses to pay the $28,000 invoice. In Alabama, what is the deadline to file a mechanics lien?

Correct Answer

A) June 29th (120 days)

Alabama lien law requires mechanics liens to be filed within 120 days of completion of work or last furnishing of materials.

Answer Options
A
June 29th (120 days)
B
August 28th (180 days)
C
February 28th of the following year (365 days)
D
May 30th (90 days)

Why This Is the Correct Answer

Option A (June 29th, 120 days) is correct. Alabama lien law requires a mechanics lien to be filed within 120 days of project completion or last furnishing of materials/services. Counting 120 days from March 1st lands on June 29th.

Why the Other Options Are Wrong

Option B: August 28th (180 days)

August 28th represents 180 days, not 120. Alabama does not use a 180-day lien filing window for general contractors. Confusing Alabama's 120-day rule with other states' longer periods is a frequent error.

Option C: February 28th of the following year (365 days)

February 28th of the following year represents 365 days (one year). Alabama's mechanics lien statute does not allow a full year for filing β€” waiting that long would cause the lien right to be lost.

Option D: May 30th (90 days)

May 30th represents 90 days. While some states and some lien types use 90-day windows, Alabama's general contractor lien deadline is 120 days, not 90.

Memory Technique

Remember '120 days in Alabama' with this phrase: 'AL has 4 months (120 days) to lien.' Four months after March 1st = July 1st minus 2 days = June 29th. Alternatively, memorize: Alabama = 120 days = 4 months.

Was this explanation helpful?

More Alabama Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.