A contractor needs to replace a damaged sidewalk in front of a commercial building. The sidewalk is in the public right-of-way. What type of permit is most likely required?
Correct Answer
B) Right-of-way permit
Work performed in public right-of-way areas typically requires a right-of-way permit from the local jurisdiction to ensure proper restoration and compliance with public infrastructure standards.
Why This Is the Correct Answer
Right-of-way permits are specifically required for any work performed within public right-of-way areas, which includes sidewalks adjacent to streets. These permits ensure that the work meets municipal standards for public infrastructure and that the area is properly restored after construction. The local jurisdiction needs to maintain control over work in these areas since they are responsible for public safety and infrastructure maintenance. This type of permit also ensures coordination with other utilities and public services that may be affected.
Why the Other Options Are Wrong
Option C: Zoning permit
While building permits are required for most construction work, they typically apply to work on private property or structures. Sidewalk replacement in the right-of-way is considered infrastructure work rather than building construction, so a specialized right-of-way permit takes precedence.
Option D: Building permit
Environmental permits are required when work may impact environmental resources like wetlands, water bodies, or protected species. Standard sidewalk replacement in an urban right-of-way typically doesn't trigger environmental permitting requirements unless there are special circumstances.
Memory Technique
ROW = Right-Of-Way work needs ROW permits. Think 'Row your boat in the ROW requires ROW permits.'
Reference Hint
Florida Building Code Chapter 1 - Scope and Administration, or local municipal code sections on right-of-way permits and public works
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
