A contractor needs to calculate the permissible exposure limit (PEL) for lead over an 8-hour workday. If air sampling shows 45 μg/m³ for 6 hours and 60 μg/m³ for 2 hours, what is the 8-hour time-weighted average?

Correct Answer

D) 48.75 μg/m³

TWA = [(45 × 6) + (60 × 2)] ÷ 8 = [270 + 120] ÷ 8 = 390 ÷ 8 = 48.75 μg/m³

Answer Options
A
47.5 μg/m³
B
55 μg/m³
C
52.5 μg/m³
D
48.75 μg/m³

Why This Is the Correct Answer

The 8-hour TWA is calculated using the formula: TWA = [(concentration₁ × time₁) + (concentration₂ × time₂)] ÷ total hours. Substituting: [(45 × 6) + (60 × 2)] ÷ 8 = [270 + 120] ÷ 8 = 390 ÷ 8 = 48.75 μg/m³. The Cal/OSHA PEL for lead is 50 μg/m³ as an 8-hour TWA. This result (48.75) is just below the PEL, meaning the Action Level (30 μg/m³) is still exceeded, which has its own compliance obligations.

Why the Other Options Are Wrong

Option A: 47.5 μg/m³

47.5 μg/m³ results from a simple average of the two concentrations: (45 + 60) ÷ 2 = 52.5, or could be from incorrectly weighting: (45 + 60) × 6/8 ≈ different wrong path. The simple average ignores the different time durations at each concentration level, which is the fundamental error the TWA formula corrects.

Option B: 55 μg/m³

55 μg/m³ is the arithmetic mean of 45 and 60 without time weighting — (45 + 60) ÷ 2 = 52.5, not 55 — or could reflect treating the 2-hour period as equal weight to the 6-hour period. Any method that ignores the unequal time periods will produce the wrong answer.

Option C: 52.5 μg/m³

52.5 μg/m³ is exactly the simple average of the two concentrations: (45 + 60) ÷ 2 = 52.5. This is the most common wrong answer because it uses the correct values but applies simple averaging instead of time-weighted averaging. In a TWA, more time at a lower concentration should pull the result lower than the arithmetic mean.

Memory Technique

TWA = Total Weighted Amount ÷ Total Hours. Calculate the total weighted amount first: multiply each concentration by its hours, add them together. Then divide by 8 (the full workday). It is a weighted average, not a simple average.

Was this explanation helpful?

More California Questions

A construction site has employees working at heights of 12 feet above the ground on a steep-slope roof. According to Cal/OSHA fall protection requirements, what must be provided?

A construction crew is working outdoors in Fresno when the temperature reaches 97°F. Under Cal/OSHA heat illness prevention requirements, what is the minimum frequency for providing preventive cool-down rest periods?

A contractor is renovating a building built in 1975 and discovers material suspected to contain asbestos. According to Cal/OSHA regulations, what is the first required action?

Under Cal/OSHA regulations, what is the minimum frequency for reviewing and updating an Injury and Illness Prevention Program (IIPP)?

Calculate the minimum shade area required for 8 construction workers during a heat illness prevention cool-down period in California:

An employee working with lead-based paint removal has a blood lead level of 45 μg/dl. According to Cal/OSHA lead standards, what action must the employer take?

An IIPP must include procedures for investigating workplace accidents. According to Cal/OSHA, who is responsible for conducting these investigations?

A competent person inspecting a trench notices water seepage and minor soil movement. Under Cal/OSHA excavation standards, what action is required?

Calculate the required air changes per hour for a confined space with lead work under Cal/OSHA regulations. The space volume is 1,200 cubic feet and the exhaust fan moves 400 CFM. How many air changes per hour are being provided?

A roofing contractor is installing fall protection on a commercial building. Under Cal/OSHA Title 8, Section 1710, at what height does fall protection become mandatory for construction work?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.