EstatePass
Business & FinanceAccountingmedium32% of exam part

A contractor is tracking costs for a commercial project with a contract value of $500,000. To date, costs incurred are $320,000 and the project is estimated to be 70% complete. What is the projected total cost at completion using the percent complete method?

Correct Answer

A) $457,143

Using the percent complete method: $320,000 ÷ 0.70 = $457,143 projected total cost. This method assumes current cost efficiency will continue through project completion.

Answer Options
A
$457,143
B
$475,000
C
$465,000
D
$485,000

Why This Is the Correct Answer

The percent complete method calculates projected total cost by dividing actual costs incurred by the percentage of work completed. With $320,000 spent at 70% completion, the formula is $320,000 ÷ 0.70 = $457,143. This method assumes the current cost efficiency rate will remain constant for the remainder of the project. It's a standard project management technique for forecasting final costs based on current performance.

Why the Other Options Are Wrong

Option B: $475,000

This answer ($465,000) appears to use an incorrect calculation method, possibly adding a fixed amount to current costs rather than using the percent complete formula. It doesn't follow the standard percent complete methodology.

Option C: $465,000

This answer ($485,000) is significantly higher than the correct calculation and indicates a fundamental misunderstanding of the percent complete method, possibly confusing it with other cost projection techniques.

Option D: $485,000

This answer ($475,000) is too high and suggests an incorrect calculation approach, possibly using a different cost projection method or mathematical error in the percent complete formula.

Memory Technique

Remember 'PCP' - Percent Complete Projection: divide actual costs BY the percent complete (as decimal) to get projected total.

Reference Hint

Look up 'Project Cost Control' or 'Earned Value Management' sections in construction management references, typically found in project management chapters.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.