A contractor is removing 400 square feet of vinyl floor tiles installed in 1975. The tiles test positive for asbestos. What is required under Cal/OSHA?
Correct Answer
D) Notification to Cal/OSHA 10 days before work begins
Cal/OSHA requires 10-day advance notification for asbestos removal projects exceeding 100 square feet of surface material.
Why This Is the Correct Answer
Cal/OSHA requires contractors to notify Cal/OSHA at least 10 working days before beginning any asbestos-related work that involves removing more than 100 square feet of asbestos-containing material. Since 400 square feet exceeds the 100-square-foot threshold, the 10-day advance notification to Cal/OSHA is a mandatory prerequisite before work begins.
Why the Other Options Are Wrong
Option A: Wet removal methods and respiratory protection
Wet removal methods and respiratory protection are indeed required during asbestos abatement, but they are not the single most critical initial requirement asked in this question. The 10-day pre-notification to Cal/OSHA must occur before any work starts β making it the foundational requirement. Wet methods and PPE are required during removal, but notification precedes everything.
Option B: No special requirements for small amounts
There are no 'small amount' exemptions from Cal/OSHA asbestos requirements when material tests positive. Any disturbing of asbestos-containing material above the regulatory threshold requires notification, trained workers, and proper procedures. The 100 sq ft threshold triggers notification β 400 sq ft clearly exceeds it.
Option C: Complete enclosure and negative air pressure
Complete enclosure and negative air pressure are required for certain high-risk asbestos operations (like Class I friable asbestos work), but vinyl floor tiles that test positive are typically addressed as Class II asbestos-containing material. The question asks what is 'required,' and the most foundational requirement is the 10-day notification β not full containment for this scenario.
Memory Technique
'10 days before, 100 sq ft is the door.' More than 100 sq ft of asbestos-containing material = notify Cal/OSHA 10 working days in advance. No exceptions, no shortcuts.
More California Questions
A construction site has employees working at heights of 12 feet above the ground on a steep-slope roof. According to Cal/OSHA fall protection requirements, what must be provided?
A construction crew is working outdoors in Fresno when the temperature reaches 97Β°F. Under Cal/OSHA heat illness prevention requirements, what is the minimum frequency for providing preventive cool-down rest periods?
A contractor is renovating a building built in 1975 and discovers material suspected to contain asbestos. According to Cal/OSHA regulations, what is the first required action?
Under Cal/OSHA regulations, what is the minimum frequency for reviewing and updating an Injury and Illness Prevention Program (IIPP)?
Calculate the minimum shade area required for 8 construction workers during a heat illness prevention cool-down period in California:
An employee working with lead-based paint removal has a blood lead level of 45 ΞΌg/dl. According to Cal/OSHA lead standards, what action must the employer take?
An IIPP must include procedures for investigating workplace accidents. According to Cal/OSHA, who is responsible for conducting these investigations?
A competent person inspecting a trench notices water seepage and minor soil movement. Under Cal/OSHA excavation standards, what action is required?
Calculate the required air changes per hour for a confined space with lead work under Cal/OSHA regulations. The space volume is 1,200 cubic feet and the exhaust fan moves 400 CFM. How many air changes per hour are being provided?
A roofing contractor is installing fall protection on a commercial building. Under Cal/OSHA Title 8, Section 1710, at what height does fall protection become mandatory for construction work?