EstatePass
Contract AdminPreconstructionmedium27% of exam part

A contractor is estimating labor costs for installing 2,000 square feet of ceramic tile. The productivity rate is 25 square feet per hour, and the labor rate is $32 per hour. What is the total labor cost?

Correct Answer

C) $2,560

Total hours needed = 2,000 sq ft ÷ 25 sq ft/hr = 80 hours. Total labor cost = 80 hours × $32/hr = $2,560.

Answer Options
A
$1,600
B
$4,800
C
$2,560
D
$3,200

Why This Is the Correct Answer

Option B is correct because it follows the proper two-step labor cost calculation method. First, we determine the total hours needed by dividing the total square footage (2,000) by the productivity rate (25 sq ft/hr), which equals 80 hours. Then we multiply those hours by the hourly labor rate ($32/hr) to get the total labor cost of $2,560.

Why the Other Options Are Wrong

Option A: $1,600

This answer ($1,600) appears to be calculated by dividing the total square footage by the hourly rate (2,000 ÷ $32 = 62.5, then rounded), which is an incorrect method that skips the productivity rate calculation entirely.

Option D: $3,200

This answer ($3,200) incorrectly multiplies the total square footage by the hourly rate (2,000 × $32 ÷ 20 = $3,200), suggesting a miscalculation in the hours needed or using wrong productivity assumptions.

Memory Technique

Remember 'DivMult' - DIVide total work by productivity rate to get hours, then MULTiply hours by hourly rate to get total cost. The units should cancel out properly: sq ft ÷ (sq ft/hr) = hr, then hr × ($/hr) = $.

Reference Hint

Construction estimating section, specifically labor productivity rates and cost calculations chapter in your contractor reference manual

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.