A contractor is estimating a project with a base cost of $2.4 million. What is the recommended contingency percentage for a design-build project in the early design phase?
Correct Answer
B) 10-20%
Design-build projects in early design phases typically require 10-20% contingency due to incomplete design information and potential scope changes as the design develops.
Why This Is the Correct Answer
Design-build projects in the early design phase require higher contingency percentages (10-20%) because the design is incomplete and evolving. Unlike traditional design-bid-build projects where designs are finalized before construction begins, design-build projects start construction while design is still developing. This creates uncertainty in scope, materials, and methods that must be accounted for with adequate contingency reserves. The 10-20% range provides sufficient buffer for design changes, unforeseen conditions, and scope modifications that commonly occur during the design development process.
Why the Other Options Are Wrong
Option C: 20-30%
5-10% contingency is still insufficient for design-build projects in early design phases, as this range would be more suitable for projects with partially developed designs or later design phases where scope is better defined.
Option D: 2-5%
2-5% contingency is too low for early design phase work and would be more appropriate for projects with completed designs and well-defined scope, such as traditional design-bid-build projects in the construction phase.
Memory Technique
Think 'Early Design = Double Digits' - early design phase design-build projects need double-digit contingency percentages (10-20%) due to design uncertainty.
Reference Hint
Look up project estimating and contingency planning sections in construction management references, typically found in chapters covering cost estimating or risk management.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Under Florida law, which entity has the authority to issue Certificates of Occupancy for new construction?
Next Question
A contractor is developing a 15-acre residential subdivision that includes wetland areas. Which agency must issue environmental permits before construction can begin?
