A contractor is developing a 15-acre residential subdivision that includes wetland areas. Which agency must issue environmental permits before construction can begin?
Correct Answer
B) South Florida Water Management District
Water Management Districts in Florida have jurisdiction over wetland permits and environmental resource permits for projects affecting wetlands. The specific district depends on the geographic location of the project.
Why This Is the Correct Answer
Water Management Districts in Florida have primary jurisdiction over wetland permitting and environmental resource permits (ERPs) for any construction activities that may impact wetlands, surface waters, or stormwater management. These districts regulate activities under Chapter 373, Florida Statutes, and are responsible for protecting water resources throughout the state. For a 15-acre residential subdivision involving wetlands, an Environmental Resource Permit from the appropriate Water Management District is mandatory before any construction can begin. The specific district (South Florida, Southwest Florida, St. Johns River, Northwest Florida, or Suwannee River) depends on the project's geographic location.
Why the Other Options Are Wrong
Option C: Local Building Department
Local Building Departments issue building permits for structures but do not have authority over environmental permits for wetland impacts - this falls under state-level Water Management District jurisdiction.
Option D: Florida Department of Health
The Florida Department of Health primarily handles septic system permits, water well permits, and public health issues, but does not have jurisdiction over wetland environmental permits for construction projects.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor is estimating a project with a base cost of $2.4 million. What is the recommended contingency percentage for a design-build project in the early design phase?
Next Question
A subcontractor's bid includes the following: Base work $85,000, Alternate #1 $12,000, Alternate #2 $8,500. The general contractor's estimate was $95,000 for base work. How should this bid be evaluated?
