A subcontractor's bid includes the following: Base work $85,000, Alternate #1 $12,000, Alternate #2 $8,500. The general contractor's estimate was $95,000 for base work. How should this bid be evaluated?
Correct Answer
C) Verify scope understanding and pricing methodology
The subcontractor's base bid is about 10% lower than the estimate, which warrants verification of scope understanding and pricing methodology to ensure no items were missed or underpriced.
Why This Is the Correct Answer
When a subcontractor's bid is significantly different from the general contractor's estimate (10% lower in this case), the prudent approach is to verify scope understanding and pricing methodology. This ensures that the subcontractor hasn't missed items, misunderstood the scope, or made pricing errors that could lead to change orders or project delays. Due diligence in bid evaluation protects both parties and the project's success.
Why the Other Options Are Wrong
Option B: Request a revised bid closer to the estimate
A 10% difference, while significant, is not automatically grounds for rejection. Many factors can cause legitimate pricing variations, and rejecting without investigation could mean losing a qualified subcontractor with competitive pricing.
Option D: Accept immediately due to lower base bid
Accepting immediately based solely on a lower price is risky and unprofessional. A bid that's 10% below estimate could indicate missing scope items, errors, or misunderstandings that will cause problems during construction.
Memory Technique
Use 'VSD' - Verify significant differences (10%+), don't just accept low bids or reject without investigation
Reference Hint
Florida Building Construction Standards and Practices - Chapter on Subcontractor Management and Bid Evaluation
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor is developing a 15-acre residential subdivision that includes wetland areas. Which agency must issue environmental permits before construction can begin?
Next Question
Under Florida Statute Chapter 713, who must receive a Notice to Owner on a private construction project?
