EstatePass
Contract AdminPermitseasy20% of exam part

Under Florida law, which entity has the authority to issue Certificates of Occupancy for new construction?

Correct Answer

B) Local building department or authorized agent

Local building departments or their authorized agents have the authority to issue Certificates of Occupancy. This authority is delegated to local jurisdictions to enforce building codes and ensure compliance.

Answer Options
A
Florida Building Commission
B
Local building department or authorized agent
C
County health department
D
State Department of Business and Professional Regulation

Why This Is the Correct Answer

Local building departments or their authorized agents are the entities responsible for issuing Certificates of Occupancy under Florida law. This authority is specifically delegated to local jurisdictions because they are responsible for enforcing building codes and conducting final inspections. The local building official has the expertise and authority to verify that construction complies with all applicable codes before allowing occupancy. This decentralized approach allows for more efficient administration and enforcement at the community level.

Why the Other Options Are Wrong

Option A: Florida Building Commission

The Florida Building Commission develops and maintains the Florida Building Code but does not issue Certificates of Occupancy for individual projects - this is a local function.

Option C: County health department

County health departments may be involved in certain aspects of construction approval (like septic systems), but they do not have the authority to issue Certificates of Occupancy.

Option D: State Department of Business and Professional Regulation

The State Department of Business and Professional Regulation oversees contractor licensing and regulation, but does not issue Certificates of Occupancy for individual construction projects.

Memory Technique

Think 'CO = Local' - Certificate of Occupancy comes from your LOCAL building department, not state agencies.

Reference Hint

Florida Building Code, Chapter 1 - Scope and Administration, Section 110 (Certificate of Occupancy)

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.