A contractor is demolishing a building constructed in 1978. Suspect asbestos-containing materials are present. Before disturbing these materials, what is required under Cal/OSHA Section 1529?

Correct Answer

C) Bulk sampling and laboratory analysis

Cal/OSHA requires bulk sampling and laboratory analysis to determine asbestos content before disturbing suspect materials in buildings constructed before 1981.

Answer Options
A
Visual inspection by qualified person
B
Air monitoring for 24 hours
C
Bulk sampling and laboratory analysis
D
Notification to building occupants only

Why This Is the Correct Answer

Cal/OSHA Section 1529 (Asbestos) requires that before any disturbance of suspect asbestos-containing material (ACM), bulk samples must be collected and submitted to an accredited laboratory for analysis. Visual inspection alone cannot confirm or rule out asbestos content — only laboratory analysis of physical samples can establish whether the material contains asbestos at or above the regulatory threshold (typically 1% by weight).

Why the Other Options Are Wrong

Option A: Visual inspection by qualified person

A visual inspection by a qualified person is insufficient to identify asbestos. Asbestos fibers are microscopic and cannot be detected by sight. While a visual inspection may identify suspect materials, it does not satisfy the requirement to determine actual asbestos content before work begins.

Option B: Air monitoring for 24 hours

Air monitoring for 24 hours is a control measure used during and after asbestos work to verify that fiber concentrations are below permissible exposure limits. It is not the initial step required before disturbing suspect materials, and it cannot tell you whether the material contains asbestos before disturbance.

Option D: Notification to building occupants only

Notification to building occupants is a required step in certain circumstances (particularly in occupied buildings), but it does not substitute for bulk sampling and laboratory analysis. Notification alone does not establish the asbestos content of the material.

Memory Technique

Remember the sequence: SAMPLE before you DISTURB. Think 'Suspect = Sample First.' The 1978 date is a clue — asbestos was widely used in construction before 1981, so pre-1981 buildings should always trigger the bulk sampling protocol.

Was this explanation helpful?

More California Questions

A construction site has employees working at heights of 12 feet above the ground on a steep-slope roof. According to Cal/OSHA fall protection requirements, what must be provided?

A construction crew is working outdoors in Fresno when the temperature reaches 97°F. Under Cal/OSHA heat illness prevention requirements, what is the minimum frequency for providing preventive cool-down rest periods?

A contractor is renovating a building built in 1975 and discovers material suspected to contain asbestos. According to Cal/OSHA regulations, what is the first required action?

Under Cal/OSHA regulations, what is the minimum frequency for reviewing and updating an Injury and Illness Prevention Program (IIPP)?

Calculate the minimum shade area required for 8 construction workers during a heat illness prevention cool-down period in California:

An employee working with lead-based paint removal has a blood lead level of 45 μg/dl. According to Cal/OSHA lead standards, what action must the employer take?

An IIPP must include procedures for investigating workplace accidents. According to Cal/OSHA, who is responsible for conducting these investigations?

A competent person inspecting a trench notices water seepage and minor soil movement. Under Cal/OSHA excavation standards, what action is required?

Calculate the required air changes per hour for a confined space with lead work under Cal/OSHA regulations. The space volume is 1,200 cubic feet and the exhaust fan moves 400 CFM. How many air changes per hour are being provided?

A roofing contractor is installing fall protection on a commercial building. Under Cal/OSHA Title 8, Section 1710, at what height does fall protection become mandatory for construction work?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.