A contractor is building near a wetland area and needs to install a temporary construction access road. The road will impact 0.3 acres of wetlands. What type of permit is likely required?
Correct Answer
A) Individual Environmental Resource Permit (ERP)
Wetland impacts of 0.3 acres typically require an Individual Environmental Resource Permit due to the size of impact. Even temporary impacts to wetlands require proper permitting and mitigation measures.
Why This Is the Correct Answer
Individual Environmental Resource Permits (ERPs) are required for wetland impacts of 0.3 acres because this exceeds the threshold for general permits or exemptions. Florida's ERP program requires individual review and permitting for impacts above certain size thresholds, typically 0.25 acres or less for general permits. Even temporary construction impacts to wetlands must be properly permitted and include mitigation measures. The 0.3-acre impact size triggers the more stringent individual permit process rather than a general permit.
Why the Other Options Are Wrong
Option B: No permit required for temporary impacts
General ERPs and exemptions are typically available only for smaller wetland impacts, usually 0.25 acres or less. At 0.3 acres, the impact size exceeds the threshold for general permits and requires the more detailed individual permit process.
Option D: General ERP or exemption
This is incorrect because Florida law requires permits for any wetland impacts, regardless of whether they are temporary or permanent. There is no exemption from permitting requirements simply because the impact is labeled as temporary.
Memory Technique
Think 'Quarter acre or less = General, More than quarter = Individual' (0.25 acres is the key threshold to remember)
Reference Hint
Florida Building Code Chapter 1, Environmental regulations section, or Environmental Resource Permit rules in Florida Administrative Code Chapter 62-330
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A quality control inspection reveals that 15 out of 200 installed electrical outlets fail to meet specifications. What is the defect rate percentage?
Next Question
A failed inspection requires re-inspection. If the standard inspection fee is $185 and re-inspections cost 150% of the original fee, what is the total cost for both inspections?