A contractor is building in an area where the design wind speed is 110 mph. According to CBC, what is the minimum required connection for roof sheathing to rafters?

Correct Answer

B) 8d common nails at 6 inches on center at edges

For 110 mph wind speeds, CBC requires 8d common nails spaced at 6 inches on center along panel edges and 12 inches on center in the field for roof sheathing attachment.

Answer Options
A
8d common nails at 4 inches on center at edges
B
8d common nails at 6 inches on center at edges
C
Ring shank nails at 4 inches on center at edges
D
10d common nails at 6 inches on center at edges

Why This Is the Correct Answer

At a design wind speed of 110 mph, CBC specifies 8d common nails at 6 inches on center at panel edges (and 12 inches on center in the field). This is the standard prescriptive requirement for this wind speed range — sufficient uplift resistance without requiring ring shank nails or larger fasteners.

Why the Other Options Are Wrong

Option A: 8d common nails at 4 inches on center at edges

8d common nails at 4 inches on center is more restrictive (tighter spacing) than the minimum required at 110 mph. While not structurally wrong, it exceeds the minimum requirement and is not what the question asks for.

Option C: Ring shank nails at 4 inches on center at edges

Ring shank nails at 4 inches on center are required in higher wind speed zones (typically 120+ mph or specific high-wind exposure categories). At 110 mph, ring shank nails are not the minimum requirement per CBC prescriptive tables.

Option D: 10d common nails at 6 inches on center at edges

10d common nails at 6 inches on center would provide more capacity than needed and are not the minimum requirement at 110 mph. Larger nail sizes are typically triggered by higher wind speeds or special exposure categories.

Memory Technique

For 110 mph wind: '8d at 6' — both numbers are common single digits. Think '110 mph = 8d/6in' as the baseline. As wind speed climbs past 120 mph, requirements escalate to ring shank or tighter spacing.

Was this explanation helpful?

More California Questions

A contractor is installing shear walls in a residence located in Seismic Design Category D. The engineer's plans call for 15/32-inch structural sheathing with 8d nails at 6 inches on center at panel edges. The contractor wants to substitute 7/16-inch OSB with the same nailing. Is this substitution acceptable?

You are reviewing plans for a mixed-use building where the ground floor will house a restaurant with commercial kitchen equipment. The architect has specified standard residential electrical requirements throughout. What Title 24 compliance issue should you identify?

According to CBC seismic provisions, what is the concept behind the 'strong column, weak beam' design philosophy?

A residence in California has 2,800 sq ft of conditioned space. The HVAC system efficiency is 16 SEER. What is the approximate Title 24 compliance margin compared to the minimum 14 SEER requirement?

You're constructing a foundation on liquefiable soils identified in a California coastal area. The geotechnical report recommends deep foundations. Which option is most commonly specified?

A contractor is installing a heat recovery ventilation (HRV) system to comply with Title 24. The system serves a 2,000 sq ft house with 3 bedrooms. What is the minimum required ventilation rate?

During construction of a basement in sandy soil conditions, you encounter groundwater at 4 feet below grade. The basement extends 8 feet below grade. What is the critical design consideration per CBC?

During a seismic retrofit project, you discover that existing concrete has a compressive strength of 2,200 psi. The engineer specifies new anchor bolts that require 2,500 psi minimum concrete strength. What is the most appropriate action?

What is the maximum allowable notch depth in a 2x10 floor joist per CBC requirements?

You're reviewing plans for a wood-framed structure in seismic design category D. The project calls for a shear wall with 15/32-inch structural sheathing and 8d nails spaced 6 inches on center at panel edges. What is the allowable shear value per the CBC?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.