EstatePass
Contract AdminPermitsmedium20% of exam part

A contractor is building a 2,500 square foot single-family residence. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the construction value is $375,000, what is the total building permit fee?

Correct Answer

A) $3,187.50

The calculation is: $375,000 ÷ $1,000 = 375 units. 375 × $8.50 = $3,187.50. This represents the standard method for calculating permit fees based on construction value.

Answer Options
A
$3,187.50
B
$3,312.50
C
$3,525.00
D
$2,975.00

Why This Is the Correct Answer

The correct answer is A) $3,187.50 because permit fees are calculated by dividing the total construction value by $1,000 to determine the number of fee units, then multiplying by the per-unit rate. With a construction value of $375,000 divided by $1,000, we get 375 units. Multiplying 375 units by $8.50 per unit equals $3,187.50.

Why the Other Options Are Wrong

Option B: $3,312.50

This answer of $3,525.00 would result from calculating approximately 415 units, which is significantly higher than the correct 375 units derived from the $375,000 construction value.

Option C: $3,525.00

This answer of $2,975.00 would result from incorrectly calculating 350 units instead of 375 units, possibly from a mathematical error in the division step.

Memory Technique

Remember 'Divide then Multiply' - always divide the construction value by 1,000 first to get your units, then multiply by the rate. Think 'D before M' like 'Dawn before Morning.'

Reference Hint

Florida Building Code Chapter 1 - Scope and Administration, Section 109 - Fees, or local jurisdiction fee schedules

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.