A contractor has annual overhead costs of $240,000 and expects to generate $1,200,000 in direct costs for the year. What is the overhead percentage that should be applied to bids?
Correct Answer
B) 20%
Overhead percentage is calculated as overhead costs divided by direct costs: $240,000 ÷ $1,200,000 = 0.20 or 20%. This percentage is then applied to direct costs in bid preparation.
Why This Is the Correct Answer
The overhead percentage is calculated by dividing total overhead costs by total direct costs. In this case, $240,000 in overhead divided by $1,200,000 in direct costs equals 0.20 or 20%. This percentage represents how much overhead cost must be added to each dollar of direct cost to cover the contractor's annual overhead expenses. The 20% overhead rate ensures that all overhead costs are properly allocated across all projects throughout the year.
Why the Other Options Are Wrong
Option A: 30%
25% would recover $300,000 in overhead costs ($1,200,000 × 0.25), which is $60,000 more than the actual overhead, potentially making bids uncompetitive.
Option C: 25%
30% would recover $360,000 in overhead costs ($1,200,000 × 0.30), which is $120,000 more than actual overhead, significantly inflating bid prices and reducing competitiveness.
Option D: 15%
15% would only recover $180,000 of overhead costs ($1,200,000 × 0.15), leaving $60,000 in overhead costs unrecovered, which would result in a loss.
Memory Technique
Think 'OH/DC' - Overhead divided by Direct Costs. Remember that overhead is always 'on top of' direct costs, so it's the numerator in the fraction.
Reference Hint
Business and Finance for Contractors - Chapter on Cost Accounting and Overhead Allocation
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
People Also Study
Related Study Resources
Previous Question
Which business entity requires the most formal record-keeping and regulatory compliance?
Next Question
A construction company has a project that started with a contract value of $500,000. To date, they have incurred costs of $300,000 and estimate $150,000 more to complete. What is the estimated gross profit on this project?
