A construction company has a project that started with a contract value of $500,000. To date, they have incurred costs of $300,000 and estimate $150,000 more to complete. What is the estimated gross profit on this project?
Correct Answer
A) $50,000
Total estimated costs = $300,000 (incurred) + $150,000 (to complete) = $450,000. Estimated gross profit = $500,000 (contract value) - $450,000 (total estimated costs) = $50,000.
Why This Is the Correct Answer
To calculate estimated gross profit, you must first determine the total estimated project costs by adding costs already incurred to the estimated costs to complete. Then subtract this total from the contract value. The calculation is: Total estimated costs = $300,000 + $150,000 = $450,000, then Gross profit = $500,000 - $450,000 = $50,000.
Why the Other Options Are Wrong
Option B: $300,000
This simply states the incurred costs to date ($300,000) as the profit, which makes no sense as it ignores both the contract value and remaining costs.
Option D: $200,000
This incorrectly uses only the estimated costs to complete ($150,000) as the gross profit, ignoring the costs already incurred. This would overstate the profit significantly.
Memory Technique
Remember 'CTC' - Contract minus Total Costs equals profit. Total costs always include both money spent AND money still needed.
Reference Hint
Look up project accounting and cost control sections in construction management references, particularly chapters on job costing and profit calculation.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
People Also Study
Related Study Resources
Previous Question
A contractor has annual overhead costs of $240,000 and expects to generate $1,200,000 in direct costs for the year. What is the overhead percentage that should be applied to bids?
Next Question
During bid preparation, a general contractor discovers that a key subcontractor has submitted a bid 30% lower than all other comparable bids. What is the most appropriate action?
