A contractor fails to pay subcontractors and suppliers totaling $75,000. Multiple claims are filed against the contractor's $15,000 bond. How are the claims resolved?
Correct Answer
C) Claims are paid proportionally up to bond limit
When claims exceed the bond amount, South Carolina law requires proportional payment to all valid claimants up to the bond limit.
Why This Is the Correct Answer
When total claims exceed the bond amount, South Carolina law requires that all valid claimants share proportionally in the available bond funds rather than paying claimants on a first-come, first-served basis. Each claimant receives a percentage of their claim equal to the bond amount divided by the total claims ($15,000 / $75,000 = 20 cents on the dollar for each claimant).
Why the Other Options Are Wrong
Option A: Only material supplier claims are paid
Paying only material supplier claims and excluding subcontractors is incorrect. South Carolina bond law does not prioritize material suppliers over subcontractors β all valid claimants (both subcontractors and suppliers) are treated equally and share proportionally.
Option B: First claim filed gets full payment
A first-filed, first-paid approach would be unfair to later-filing claimants and is not the rule under South Carolina law. The statute is designed to treat all valid claimants equitably when funds are insufficient to cover all claims.
Option D: Bond is invalid for multiple claims
Bonds are not invalidated simply because multiple claims are filed or because claims exceed the bond amount. A bond remains valid and enforceable; it simply limits the total payout to its face value, which is then distributed proportionally.
Memory Technique
Think of the bond as a pie that must be sliced equally among all guests. If there are more guests than the pie can feed, everyone gets a smaller slice β no one guest gets a full piece while others get nothing. Pro-rata = proportional sharing of whatever is available.
More South Carolina Questions
What is the maximum contract value a Tier 1 residential contractor can undertake in South Carolina?
Under South Carolina law, a contractor discovers a material defect in their work 6 months after project completion. The owner demands immediate correction. What is the contractor's legal obligation?
A contractor has 15 employees and annual payroll of $780,000. The workers compensation rate is $4.25 per $100 of payroll. What is the annual premium?
According to SC building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?
A subcontractor completes $25,000 of electrical work but is not paid by the general contractor. The general contractor was paid by the owner. What is the subcontractor's lien priority against the property?
A contractor receives a stop work order from the building official. Work continues for 3 additional days before stopping. What penalty applies per South Carolina building codes?
Under South Carolina workers compensation law, which of the following employees would be exempt from coverage requirements?
Under South Carolina contractor licensing law, how many hours of continuing education are required annually for license renewal?
A Class B contractor wants to bid on a $750,000 commercial project. What must the contractor do to be eligible?
A contractor's license expires on June 30th. They submit renewal application and fees on July 15th. What additional penalty must they pay?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A subcontractor's workers compensation policy costs $18,000 annually for a payroll of $400,000. If the payroll increases to $520,000, what will be the new annual premium cost?
Next Question
A material supplier delivers $25,000 worth of lumber to a construction project but is not paid. Under South Carolina mechanics lien law, when must the supplier file their lien notice?