A contractor fails to pay subcontractors and suppliers totaling $75,000. Multiple claims are filed against the contractor's $15,000 bond. How are the claims resolved?

Correct Answer

C) Claims are paid proportionally up to bond limit

When claims exceed the bond amount, South Carolina law requires proportional payment to all valid claimants up to the bond limit.

Answer Options
A
Only material supplier claims are paid
B
First claim filed gets full payment
C
Claims are paid proportionally up to bond limit
D
Bond is invalid for multiple claims

Why This Is the Correct Answer

When claims exceed the bond amount, South Carolina law requires proportional payment to all valid claimants up to the bond limit.

Was this explanation helpful?

More sc-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.