A contractor enters into a Guaranteed Maximum Price (GMP) contract for $2,400,000 with a shared savings provision of 50/50 split. The actual cost of work is $2,250,000. How much will the contractor receive as their share of savings?
Correct Answer
C) $75,000
Savings = $2,400,000 - $2,250,000 = $150,000. With 50/50 split, contractor receives $150,000 ÷ 2 = $75,000.
Why This Is the Correct Answer
Total savings = GMP minus actual cost = $2,400,000 − $2,250,000 = $150,000. With a 50/50 shared savings split, the contractor's share = $150,000 ÷ 2 = $75,000. The contractor does not receive the entire savings; they split it equally with the owner.
Why the Other Options Are Wrong
Option A: $225,000
$225,000 appears to be 10% of the GMP, which has no basis in the problem's calculation. It may result from a misapplied percentage or a miscalculation of the savings total.
Option B: $300,000
$300,000 might come from taking 10% of some combined figure or incorrectly calculating savings as a different base amount. It is not derived from the correct $150,000 savings figure.
Option D: $150,000
$150,000 is the total savings amount — the full difference between GMP and actual cost. This is a trap for candidates who forget to apply the 50/50 split to arrive at the contractor's portion. The $150,000 must be divided by 2.
Memory Technique
GMP Shared Savings formula: Savings = GMP − Actual. Contractor's Share = Savings × Contractor's Percentage. Two steps, never skip the split. '$150K savings ÷ 2 partners = $75K each.'
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
During framing inspection, you notice that the carpenter has notched a 2×10 floor joist at mid-span. The notch is 2 inches deep on the bottom edge. What should be your response?
Next Question
When allocating labor resources across multiple concurrent activities, what is the most important factor to consider?
