A contractor discovers that their workers compensation insurance has lapsed during an active project. What action must they take immediately under South Carolina law?
Correct Answer
D) Stop all work immediately until coverage is restored
South Carolina law requires contractors to immediately cease all work when workers compensation coverage lapses, as continuing work without coverage violates state requirements.
Why This Is the Correct Answer
South Carolina law requires contractors to maintain continuous workers compensation coverage whenever employees are working. When coverage lapses, the contractor must immediately stop all work. Continuing to operate without workers comp exposes employees to uninsured risk and exposes the contractor to severe legal and financial penalties. There is no grace period.
Why the Other Options Are Wrong
Option A: Purchase coverage within 10 days
A 10-day window to purchase coverage does not exist in South Carolina law. Any continuation of work during a lapse in coverage is a violation, regardless of how quickly the contractor intends to reinstate insurance.
Option B: Continue work but notify the client
Continuing work while notifying the client is not a legal option. Notification does not create insurance coverage or satisfy the legal requirement. The client's awareness does not protect employees or the contractor.
Option C: Complete the current phase then stop work
Completing a current phase before stopping is still a continuation of uninsured work. SC law does not recognize project milestones as justification for operating without workers comp.
Memory Technique
No coverage = No work. Period. Think of it as a light switch: coverage off → work must stop. It doesn't matter if you're mid-pour on a concrete slab — the law doesn't care about project phases.
More South Carolina Questions
What is the maximum contract value a Tier 1 residential contractor can undertake in South Carolina?
Under South Carolina law, a contractor discovers a material defect in their work 6 months after project completion. The owner demands immediate correction. What is the contractor's legal obligation?
A contractor has 15 employees and annual payroll of $780,000. The workers compensation rate is $4.25 per $100 of payroll. What is the annual premium?
According to SC building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?
A subcontractor completes $25,000 of electrical work but is not paid by the general contractor. The general contractor was paid by the owner. What is the subcontractor's lien priority against the property?
A contractor receives a stop work order from the building official. Work continues for 3 additional days before stopping. What penalty applies per South Carolina building codes?
Under South Carolina workers compensation law, which of the following employees would be exempt from coverage requirements?
Under South Carolina contractor licensing law, how many hours of continuing education are required annually for license renewal?
A Class B contractor wants to bid on a $750,000 commercial project. What must the contractor do to be eligible?
A contractor's license expires on June 30th. They submit renewal application and fees on July 15th. What additional penalty must they pay?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Under SC building codes, what is the minimum required fire rating for a wall separating a garage from living space in a residential building?
Next Question
A contractor files a mechanics lien on March 15th for work completed on February 1st. The property owner files for lien release. Within how many days must the contractor file suit to enforce the lien?