EstatePass
Contract AdminPermitsmedium20% of exam part

A contractor discovers that the project site contains protected wetlands during excavation. What is the most appropriate immediate action?

Correct Answer

A) Stop work and contact the appropriate environmental agency

Work must stop immediately and the appropriate environmental agency must be contacted. Continuing any work could result in severe penalties and environmental violations under state and federal law.

Answer Options
A
Stop work and contact the appropriate environmental agency
B
Continue work but avoid the wetland area
C
Relocate the building to another part of the site
D
Complete the foundation work quickly before reporting

Why This Is the Correct Answer

When protected wetlands are discovered during construction, federal and state environmental laws require immediate cessation of all work activities. The contractor must notify the appropriate environmental agencies (such as the Army Corps of Engineers or Florida DEP) to assess the situation and determine proper remediation procedures. Continuing any work in or near wetlands without proper permits can result in severe civil and criminal penalties, including substantial fines and project shutdowns. This is a strict liability situation where immediate compliance is mandatory.

Why the Other Options Are Wrong

Option B: Continue work but avoid the wetland area

Continuing work in any capacity, even avoiding the wetland area, violates environmental protection laws and can result in severe penalties. The entire site may be affected by wetland boundaries and buffer zones that extend beyond the visible wetland area.

Option D: Complete the foundation work quickly before reporting

Relocating the building without proper environmental assessment and agency approval is still a violation. The contractor cannot make unilateral decisions about site modifications when protected wetlands are involved - all changes must be approved by environmental agencies.

Memory Technique

Think 'WETLANDS = STOP SIGN' - just like you can't run a stop sign, you can't continue work when wetlands are discovered. Both require immediate stopping and following proper procedures.

Reference Hint

Florida Building Code Chapter 1, Administration section on environmental compliance, and Environmental Protection statutes in Florida Statutes Chapter 373

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.