A contractor discovers that the project site contains protected wetlands during excavation. What is the most appropriate immediate action?
Correct Answer
A) Stop work and contact the appropriate environmental agency
Work must stop immediately and the appropriate environmental agency must be contacted. Continuing any work could result in severe penalties and environmental violations under state and federal law.
Why This Is the Correct Answer
When protected wetlands are discovered during construction, federal and state environmental laws require immediate cessation of all work activities. The contractor must notify the appropriate environmental agencies (such as the Army Corps of Engineers or Florida DEP) to assess the situation and determine proper remediation procedures. Continuing any work in or near wetlands without proper permits can result in severe civil and criminal penalties, including substantial fines and project shutdowns. This is a strict liability situation where immediate compliance is mandatory.
Why the Other Options Are Wrong
Option B: Continue work but avoid the wetland area
Continuing work in any capacity, even avoiding the wetland area, violates environmental protection laws and can result in severe penalties. The entire site may be affected by wetland boundaries and buffer zones that extend beyond the visible wetland area.
Option D: Complete the foundation work quickly before reporting
Relocating the building without proper environmental assessment and agency approval is still a violation. The contractor cannot make unilateral decisions about site modifications when protected wetlands are involved - all changes must be approved by environmental agencies.
Memory Technique
Think 'WETLANDS = STOP SIGN' - just like you can't run a stop sign, you can't continue work when wetlands are discovered. Both require immediate stopping and following proper procedures.
Reference Hint
Florida Building Code Chapter 1, Administration section on environmental compliance, and Environmental Protection statutes in Florida Statutes Chapter 373
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A general contractor receives a change order request that will add $45,000 to the contract price and extend the schedule by 12 days. The original contract was for $850,000 with a 180-day duration. What percentage increase does this represent to the original contract value?
Next Question
When estimating equipment costs, what is the break-even point for purchasing versus renting a piece of equipment?
