EstatePass
MichiganBusinesshard50% of exam part

A contractor completes work on March 15th but the property owner doesn't make final payment. Under Michigan's Construction Lien Act 497, what is the last day the contractor can record a lien claim?

Correct Answer

C) June 13th

Under Michigan's Construction Lien Act 497, a lien claim must be recorded within 90 days of completion. 90 days from March 15th is June 13th.

Answer Options
A
July 15th
B
June 15th
C
June 13th
D
July 13th

Why This Is the Correct Answer

Michigan's Construction Lien Act (Act 497) requires a contractor to record a lien claim within 90 days of the last date labor or materials were furnished. Starting from March 15th and counting forward exactly 90 days: March has 31 days, so 16 remaining days in March after the 15th; April has 30 days; May has 31 days; and then into June. 16 (March) + 30 (April) + 31 (May) = 77 days, leaving 13 more days into June — arriving at June 13th. This is the correct deadline.

Why the Other Options Are Wrong

Option A: July 15th

July 15th would represent approximately 122 days after March 15th — far beyond the 90-day statutory window. By July 15th, the lien right would have already expired under Act 497.

Option B: June 15th

June 15th is 92 days after March 15th, which exceeds the 90-day deadline by 2 days. The lien would already be time-barred if filed on June 15th. This answer results from rounding to a 'clean' date without precise counting.

Option D: July 13th

July 13th is approximately 120 days after March 15th — well beyond the 90-day filing window. This answer reflects confusion between the 90-day recording period and some other deadline.

Memory Technique

Use the finger-counting method for months (March=31, April=30, May=31) and subtract the starting date: (31-15) + 30 + 31 = 16 + 30 + 31 = 77 days through May 31. Remaining: 90 - 77 = 13 days into June = June 13th. Practice this arithmetic — it is a skill tested repeatedly on construction lien questions.

Was this explanation helpful?

More Michigan Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.