A contractor completes work on March 15th but the property owner doesn't make final payment. Under Michigan's Construction Lien Act 497, what is the last day the contractor can record a lien claim?

Correct Answer

C) June 13th

Under Michigan's Construction Lien Act 497, a lien claim must be recorded within 90 days of completion. 90 days from March 15th is June 13th.

Answer Options
A
July 15th
B
June 15th
C
June 13th
D
July 13th

Why This Is the Correct Answer

Under Michigan's Construction Lien Act 497, a lien claim must be recorded within 90 days of completion. 90 days from March 15th is June 13th.

Was this explanation helpful?

More mi-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.