EstatePass
Contract AdminPermitshard20% of exam part

A contractor applies for a building permit on Monday. The local building department has 30 calendar days to review the application. If no response is received by the deadline, what happens to the permit application?

Correct Answer

A) The application is automatically approved

Under Florida law, if a building department does not respond to a permit application within the specified timeframe (typically 30 days), the application is deemed automatically approved. This prevents unnecessary delays in the permitting process.

Answer Options
A
The application is automatically approved
B
The contractor must resubmit the application
C
The application is automatically denied
D
The review period is extended by 15 days

Why This Is the Correct Answer

Florida Statutes Section 125.022 and 166.033 establish the 'deemed approved' rule for building permits. This statutory provision ensures that local governments cannot indefinitely delay construction projects by failing to act on permit applications. The automatic approval mechanism protects contractors and property owners from bureaucratic delays while still allowing reasonable time for proper review. This rule applies when the building department fails to approve, approve with conditions, or deny the application within the specified timeframe.

Why the Other Options Are Wrong

Option C: The application is automatically denied

Automatic denial would be counterproductive and unfair to applicants, as it would penalize them for the building department's failure to act timely. Florida law specifically protects against this outcome.

Option D: The review period is extended by 15 days

There is no provision in Florida law for automatic extensions of the review period. The 30-day timeframe is firm, and failure to act results in deemed approval, not extended review time.

Memory Technique

Think 'No News is Good News' - when the building department gives you no response by the deadline, that's good news because it means automatic approval.

Reference Hint

Florida Statutes Chapter 125.022 (counties) and 166.033 (municipalities) - Local Government Comprehensive Planning sections

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.