EstatePass
Contract AdminPreconstructioneasy27% of exam part

What is the recommended contingency percentage for renovation work compared to new construction?

Correct Answer

C) Higher for renovation work

Renovation work typically requires higher contingency percentages due to unknown existing conditions, potential hazardous materials, and integration challenges with existing systems.

Answer Options
A
Same percentage for both
B
Lower for renovation work
C
Higher for renovation work
D
Contingency is not needed for renovation

Why This Is the Correct Answer

Renovation work requires higher contingency percentages because contractors encounter numerous unforeseen conditions when working with existing structures. Hidden structural issues, outdated electrical or plumbing systems, asbestos or lead paint, and the challenge of integrating new work with existing systems create significant cost uncertainty. While new construction typically uses 5-10% contingency, renovation projects often require 15-25% or higher contingencies to account for these unknown variables.

Why the Other Options Are Wrong

Option A: Same percentage for both

Lower contingency for renovation work would be financially irresponsible, as renovation projects consistently present more surprises and unforeseen conditions that require additional time and materials to address.

Option B: Lower for renovation work

Contingency is especially critical for renovation work due to the high likelihood of encountering unexpected conditions, making this option completely incorrect and potentially financially disastrous.

Memory Technique

Think 'R.I.P.' for Renovation: Renovation = Increased Problems = higher contingency Percentage

Reference Hint

Look up project estimating and cost control sections, typically found in construction management or estimating chapters of contractor reference materials.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.