A complex project has multiple critical paths with durations of 180, 185, and 190 days respectively. The project experiences a 3-day delay on the path with 185-day duration. What is the new project duration?
Correct Answer
C) 190 days
The project duration is determined by the longest path. The 190-day path remains the critical path, so the project duration stays at 190 days since the delayed path (188 days) is still shorter.
Why This Is the Correct Answer
CORRECT_ANSWER - In project management, the overall project duration is always determined by the longest critical path. Even though the 185-day path experienced a 3-day delay making it 188 days, the 190-day path remains unchanged and is still the longest. Since 190 days > 188 days > 180 days, the project duration remains 190 days.
Why the Other Options Are Wrong
Option A: 188 days
193 days incorrectly adds the 3-day delay to the longest path (190 + 3), but the delay occurred on the 185-day path, not the 190-day path.
Option B: 193 days
185 days represents the original duration of the delayed path, but this ignores both the delay that occurred and the fact that there's a longer 190-day path that determines the overall project duration.
Memory Technique
Remember 'LPR' - Longest Path Rules. The project is only as fast as its slowest (longest) path, just like a chain is only as strong as its weakest link.
Reference Hint
Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management or project management chapters
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor applies for a building permit on Monday. The local building department has 30 calendar days to review the application. If no response is received by the deadline, what happens to the permit application?
Next Question
During a construction coordination meeting, the electrical subcontractor reports they cannot install panels until the drywall is complete, but the drywall contractor needs electrical rough-in first. What should the general contractor do?
