EstatePass
Contract AdminProceduresmedium13% of exam part

During a construction coordination meeting, the electrical subcontractor reports they cannot install panels until the drywall is complete, but the drywall contractor needs electrical rough-in first. What should the general contractor do?

Correct Answer

B) Clarify the proper sequence and coordinate the schedule

The general contractor should clarify the proper construction sequence (electrical rough-in before drywall, electrical panels after drywall) and coordinate the schedule accordingly. This prevents conflicts and ensures proper work flow.

Answer Options
A
Delay both trades until the issue resolves itself
B
Clarify the proper sequence and coordinate the schedule
C
Tell the electrical contractor to work around the drywall
D
Hire additional workers to speed up both trades

Why This Is the Correct Answer

Option B is correct because the general contractor's primary responsibility is project coordination and scheduling. The GC must understand that electrical work occurs in two phases: rough-in (before drywall) and finish work including panels (after drywall). By clarifying the proper sequence and coordinating the schedule, the GC ensures both trades can work efficiently without conflicts. This demonstrates proper project management and prevents costly delays or rework.

Why the Other Options Are Wrong

Option A: Delay both trades until the issue resolves itself

Passive delay without action fails the GC's duty to actively manage and coordinate the project. This approach wastes time, increases costs, and doesn't address the underlying scheduling confusion that caused the conflict.

Option D: Hire additional workers to speed up both trades

This option ignores proper construction sequencing and could result in code violations, safety issues, and poor workmanship. Electrical panels cannot be properly installed without access behind walls, and forcing trades to work around each other creates inefficiency and potential conflicts.

Memory Technique

Think 'ROUGH before ROCK' - electrical rough-in comes before drywall (sheetrock), then electrical finish work comes after drywall is complete

Reference Hint

Florida Building Code Chapter 1, Project Management and Coordination sections, or Construction Management reference materials covering trade sequencing

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.