A contract includes liquidated damages of $2,000 per day but caps the total at 10% of the contract value. For a $1.2 million contract delayed 75 days, what is the maximum liquidated damages that can be assessed?
Correct Answer
D) $120,000
Calculated damages: 75 days × $2,000 = $150,000. Contract cap: $1,200,000 × 10% = $120,000. The cap limits damages to $120,000.
Why This Is the Correct Answer
This problem requires calculating both the total liquidated damages based on daily rate and the contract cap, then applying whichever is lower. The daily calculation gives $150,000 (75 days × $2,000), but the 10% contract cap limits damages to $120,000 ($1,200,000 × 10%). Since contract caps are maximum limits, the lower amount of $120,000 applies.
Why the Other Options Are Wrong
Option A: $100,000
This incorrectly calculates liquidated damages as $1,000 per day instead of the stated $2,000 per day (75 × $1,000 = $75,000), showing a misreading of the daily rate.
Option C: $150,000
This represents the uncapped liquidated damages calculation (75 days × $2,000 = $150,000) but ignores the 10% contract value cap that limits the total damages to a lower amount.
Memory Technique
Remember 'CAP means CHOP' - when you hit the percentage cap, you chop off any excess damages above that limit, regardless of how the daily calculation adds up.
Reference Hint
Florida Building Code Chapter 1, Section 107 - Construction Documents and Permits, or contract law sections covering liquidated damages provisions
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
