EstatePass
CaliforniaSafetymedium20% of exam part

A construction site in Fresno reaches an ambient temperature of 95°F with 40% humidity. According to Cal/OSHA heat illness prevention requirements, what is the minimum frequency for providing water breaks to employees performing moderate work?

Correct Answer

C) Every 15 minutes

At 95°F, Cal/OSHA requires water breaks every 15 minutes for employees performing moderate to heavy work to prevent heat illness.

Answer Options
A
Every 30 minutes
B
Every 2 hours
C
Every 15 minutes
D
Every hour

Why This Is the Correct Answer

At 95°F, Cal/OSHA heat illness prevention regulations require employees performing moderate to heavy work to receive water breaks at a minimum frequency of every 15 minutes. This threshold temperature triggers the most frequent mandatory hydration schedule to prevent heat exhaustion and heat stroke.

Why the Other Options Are Wrong

Option A: Every 30 minutes

Every 30 minutes is not sufficient at 95°F. While 30-minute intervals might apply at lower temperature thresholds, once the temperature reaches 95°F the regulation requires water every 15 minutes for moderate or heavy exertion.

Option B: Every 2 hours

Every 2 hours is far too infrequent at 95°F and would put workers at serious risk of heat illness. No Cal/OSHA heat regulation allows such long gaps between water breaks in high-temperature conditions.

Option D: Every hour

Every hour is not compliant at 95°F. Hourly water breaks may be a common informal practice but do not meet the 15-minute requirement triggered at this temperature for moderate or heavy work.

Memory Technique

95°F = 15-minute water breaks. Both numbers end in 5. At 95, you get a water break every 15. Easy pairing to memorize.

Was this explanation helpful?

More California Questions

A construction site has employees working at heights of 12 feet above the ground on a steep-slope roof. According to Cal/OSHA fall protection requirements, what must be provided?

A construction crew is working outdoors in Fresno when the temperature reaches 97°F. Under Cal/OSHA heat illness prevention requirements, what is the minimum frequency for providing preventive cool-down rest periods?

A contractor is renovating a building built in 1975 and discovers material suspected to contain asbestos. According to Cal/OSHA regulations, what is the first required action?

Under Cal/OSHA regulations, what is the minimum frequency for reviewing and updating an Injury and Illness Prevention Program (IIPP)?

Calculate the minimum shade area required for 8 construction workers during a heat illness prevention cool-down period in California:

An employee working with lead-based paint removal has a blood lead level of 45 μg/dl. According to Cal/OSHA lead standards, what action must the employer take?

An IIPP must include procedures for investigating workplace accidents. According to Cal/OSHA, who is responsible for conducting these investigations?

A competent person inspecting a trench notices water seepage and minor soil movement. Under Cal/OSHA excavation standards, what action is required?

Calculate the required air changes per hour for a confined space with lead work under Cal/OSHA regulations. The space volume is 1,200 cubic feet and the exhaust fan moves 400 CFM. How many air changes per hour are being provided?

A roofing contractor is installing fall protection on a commercial building. Under Cal/OSHA Title 8, Section 1710, at what height does fall protection become mandatory for construction work?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.