A construction project involves removing 150 square feet of acoustic ceiling tiles installed in 1975. Testing reveals 2% asbestos content. What Cal/OSHA notification requirement applies?

Correct Answer

B) 10-day advance notification to Cal/OSHA

Cal/OSHA requires 10-day advance notification for asbestos removal projects involving more than 100 square feet of asbestos-containing material.

Answer Options
A
30-day advance notification to Cal/OSHA
B
10-day advance notification to Cal/OSHA
C
No notification required
D
24-hour advance notification to Cal/OSHA

Why This Is the Correct Answer

Cal/OSHA requires 10-day advance notification to the agency before beginning asbestos removal work that involves more than 100 square feet of asbestos-containing material (ACM). This project involves 150 square feet at 2% asbestos content, which exceeds the 100 square foot threshold and triggers the mandatory 10-day advance notice.

Why the Other Options Are Wrong

Option A: 30-day advance notification to Cal/OSHA

30-day advance notification is not the Cal/OSHA standard. This figure may be confused with EPA NESHAP or other environmental regulations that require 10 business days (which can approximate 14 calendar days). Cal/OSHA specifically requires 10 days, not 30.

Option C: No notification required

No notification is incorrect. With 150 square feet of ACM (exceeding the 100 sq ft threshold), notification is absolutely required. Failing to notify Cal/OSHA before beginning this work would be a serious violation.

Option D: 24-hour advance notification to Cal/OSHA

24-hour advance notification is far too short for a project of this scope. A 24-hour window applies to emergency or unplanned situations under certain hazardous material regulations, not to planned asbestos abatement projects over 100 square feet.

Memory Technique

100 sq ft = notification trigger. 10 days = notice period. Both involve the number 10. Over 100 sq ft β†’ 10-day notice to Cal/OSHA.

Was this explanation helpful?

More California Questions

A construction site has employees working at heights of 12 feet above the ground on a steep-slope roof. According to Cal/OSHA fall protection requirements, what must be provided?

A construction crew is working outdoors in Fresno when the temperature reaches 97Β°F. Under Cal/OSHA heat illness prevention requirements, what is the minimum frequency for providing preventive cool-down rest periods?

A contractor is renovating a building built in 1975 and discovers material suspected to contain asbestos. According to Cal/OSHA regulations, what is the first required action?

Under Cal/OSHA regulations, what is the minimum frequency for reviewing and updating an Injury and Illness Prevention Program (IIPP)?

Calculate the minimum shade area required for 8 construction workers during a heat illness prevention cool-down period in California:

An employee working with lead-based paint removal has a blood lead level of 45 ΞΌg/dl. According to Cal/OSHA lead standards, what action must the employer take?

An IIPP must include procedures for investigating workplace accidents. According to Cal/OSHA, who is responsible for conducting these investigations?

A competent person inspecting a trench notices water seepage and minor soil movement. Under Cal/OSHA excavation standards, what action is required?

Calculate the required air changes per hour for a confined space with lead work under Cal/OSHA regulations. The space volume is 1,200 cubic feet and the exhaust fan moves 400 CFM. How many air changes per hour are being provided?

A roofing contractor is installing fall protection on a commercial building. Under Cal/OSHA Title 8, Section 1710, at what height does fall protection become mandatory for construction work?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.