A construction project involves removal of lead-based paint from a bridge built in 1960. The 8-hour TWA exposure measurement shows 40 μg/m³. What action is required under Cal/OSHA?

Correct Answer

A) Provide medical surveillance and implement controls

At 40 μg/m³, the exposure exceeds the action level (30 μg/m³) but is below the PEL (50 μg/m³), requiring medical surveillance and exposure control implementation.

Answer Options
A
Provide medical surveillance and implement controls
B
No special action required
C
Implement exposure control measures
D
Stop work immediately

Why This Is the Correct Answer

Under Cal/OSHA Section 1532.1, the Action Level (AL) for lead is 30 μg/m³ and the Permissible Exposure Limit (PEL) is 50 μg/m³. At 40 μg/m³, the exposure exceeds the AL but is below the PEL. This triggers requirements for medical surveillance and implementation of engineering/administrative controls to reduce exposure.

Why the Other Options Are Wrong

Option B: No special action required

No action required is incorrect. Even at 40 μg/m³ — below the PEL — the Action Level of 30 μg/m³ has been exceeded, triggering mandatory medical surveillance and exposure control requirements.

Option C: Implement exposure control measures

Implementing exposure control measures alone is insufficient at this level. Once the Action Level is exceeded, medical surveillance is also required — not just engineering controls.

Option D: Stop work immediately

Stopping work immediately would be appropriate if the PEL of 50 μg/m³ were exceeded without adequate controls in place. At 40 μg/m³ (below the PEL), work may continue with appropriate controls and medical monitoring.

Memory Technique

Lead ladder: 30 AL → both surveillance AND controls kick in. 50 PEL → full compliance mandatory. Think of 30 as the 'alert' and 50 as the 'alarm.' At 40, you're between the two — alert mode: monitor people AND control exposure.

Was this explanation helpful?

More California Questions

A construction site has employees working at heights of 12 feet above the ground on a steep-slope roof. According to Cal/OSHA fall protection requirements, what must be provided?

A construction crew is working outdoors in Fresno when the temperature reaches 97°F. Under Cal/OSHA heat illness prevention requirements, what is the minimum frequency for providing preventive cool-down rest periods?

A contractor is renovating a building built in 1975 and discovers material suspected to contain asbestos. According to Cal/OSHA regulations, what is the first required action?

Under Cal/OSHA regulations, what is the minimum frequency for reviewing and updating an Injury and Illness Prevention Program (IIPP)?

Calculate the minimum shade area required for 8 construction workers during a heat illness prevention cool-down period in California:

An employee working with lead-based paint removal has a blood lead level of 45 μg/dl. According to Cal/OSHA lead standards, what action must the employer take?

An IIPP must include procedures for investigating workplace accidents. According to Cal/OSHA, who is responsible for conducting these investigations?

A competent person inspecting a trench notices water seepage and minor soil movement. Under Cal/OSHA excavation standards, what action is required?

Calculate the required air changes per hour for a confined space with lead work under Cal/OSHA regulations. The space volume is 1,200 cubic feet and the exhaust fan moves 400 CFM. How many air changes per hour are being provided?

A roofing contractor is installing fall protection on a commercial building. Under Cal/OSHA Title 8, Section 1710, at what height does fall protection become mandatory for construction work?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.