A construction project has activities with the following durations: A=5 days, B=8 days, C=6 days, D=4 days. Path 1 is A-C-D and Path 2 is B-D. What is the critical path duration?
Correct Answer
C) 15 days
Path 1 (A-C-D) = 5+6+4 = 15 days. Path 2 (B-D) = 8+4 = 12 days. The critical path is the longest path, which is Path 1 at 15 days.
Why This Is the Correct Answer
The critical path is the longest path through the project network. Path 1 (A-C-D) totals 5+6+4 = 15 days, while Path 2 (B-D) totals 8+4 = 12 days. Since Path 1 takes 15 days and Path 2 takes 12 days, the critical path duration is 15 days, making option B correct.
Why the Other Options Are Wrong
Option A: 12 days
12 days represents the duration of Path 2 (B-D = 8+4), which is the shorter path. This is not the critical path since the critical path must be the longest path through the network.
Option D: 19 days
23 days is incorrect and significantly higher than either path duration. This could result from adding all activities together (5+8+6+4=23) instead of following the specific path sequences provided.
Memory Technique
Remember 'CRITICAL = LONGEST' - the critical path is always the path with the longest total duration through the project network.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
