A construction company discovers that actual labor costs on a project are running 15% over budget when 60% of the work is complete. If the original labor budget was $200,000, what is the projected final labor cost variance?
Correct Answer
C) $50,000 over budget
At 60% complete, actual costs should be $120,000 but are 15% over = $138,000. Projected total = $138,000 ÷ 0.60 = $230,000. Variance = $230,000 - $200,000 = $30,000. Wait, let me recalculate: If 15% over throughout, final cost = $200,000 × 1.15 = $230,000. Variance = $30,000. The answer should be A, but given the options, B might reflect a different calculation method.
Why This Is the Correct Answer
At 60% complete, actual costs should be $120,000 but are 15% over = $138,000. Projected total = $138,000 ÷ 0.60 = $230,000. Variance = $230,000 - $200,000 = $30,000. Wait, let me recalculate: If 15% over throughout, final cost = $200,000 × 1.15 = $230,000. Variance = $30,000. The answer should be A, but given the options, B might reflect a different calculation method.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
