A competent person conducting daily scaffold inspections discovers a loose guardrail connection. What action must be taken?
Correct Answer
A) Immediately prohibit access until the defect is corrected
OSHA 29 CFR 1926.451(f)(3) requires that any defects discovered during scaffold inspections be corrected before the scaffold is used. Access must be prohibited until corrections are made.
Why This Is the Correct Answer
Option A is correct. OSHA 29 CFR 1926.451(f)(3) is explicit: scaffolding with defects found during inspection must be immediately taken out of service and access prohibited until the defect is corrected. There is no provision for partial use, tiered access by experience level, or delayed reporting. The standard is absolute — defect discovered = work stops.
Why the Other Options Are Wrong
Option B: Allow experienced workers only in that area
Allowing only experienced workers in a defective area is not permitted under OSHA. Scaffold safety standards apply equally regardless of worker experience level. A loose guardrail can fail for anyone — experience does not reduce the fall hazard. This option is a common 'common sense' trap that contradicts the regulation.
Option C: Report it at the end of the shift
Reporting at the end of the shift means workers could be exposed to the defective scaffold for an entire shift. OSHA requires immediate action upon discovery of a defect — not deferred reporting. The purpose of daily inspections is to catch hazards before work begins or to halt work immediately if a hazard is found mid-shift.
Option D: Tag the area and continue work on other parts of the scaffold
Tagging the area and continuing work on other parts of the scaffold does not eliminate the hazard. Workers moving on the scaffold could inadvertently enter the tagged area, and the loose guardrail could affect scaffold stability across a larger section. OSHA's requirement is to prohibit all access to the defective scaffold, not to work around the defect.
Memory Technique
Remember OSHA's scaffold rule as 'STOP and FIX': Scaffold defect → STOP all access → FIX the defect → RESUME work. There is no 'continue carefully' option. Think of a red traffic light — no one gets to run it based on experience.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
In competitive bidding, what is the primary risk of applying too low a profit margin?
Next Question
A site requires 2,400 cubic yards of compacted fill. The soil has a shrinkage factor of 15% from bank to compacted state. How many cubic yards of material must be excavated from the borrow pit?