EstatePass
Contract AdminPermitseasy20% of exam part

A Certificate of Occupancy (CO) cannot be issued until which of the following conditions is met?

Correct Answer

D) All required inspections have been completed and approved

A Certificate of Occupancy can only be issued after all required inspections have been completed and approved by the building department. This ensures the building meets all code requirements for safe occupancy.

Answer Options
A
The building has been occupied for 30 days without issues
B
All subcontractors have been paid in full
C
The contractor's license has been renewed
D
All required inspections have been completed and approved

Why This Is the Correct Answer

A Certificate of Occupancy (CO) is a legal document issued by the building department that certifies a building is safe for occupancy and complies with all applicable building codes. The CO can only be issued after all required inspections (structural, electrical, plumbing, mechanical, fire safety, etc.) have been completed and approved. This is a mandatory prerequisite that ensures the building meets all safety standards before anyone can legally occupy the structure.

Why the Other Options Are Wrong

Option A: The building has been occupied for 30 days without issues

Payment of subcontractors is a contractual and financial matter between the general contractor and subcontractors, but it has no bearing on whether a building is safe for occupancy. The building department does not verify payment status when issuing a CO.

Option C: The contractor's license has been renewed

The contractor's license renewal status is unrelated to the building's readiness for occupancy. A CO is about the building's compliance with safety codes, not the contractor's licensing status. The building department focuses on the structure's safety, not contractor credentials when issuing a CO.

Memory Technique

Think 'CO before you GO' - Certificate of Occupancy must come before anyone can GO into the building, and it requires all inspections to be Complete and OK (CO).

Reference Hint

Florida Building Code, Chapter 1 - Scope and Administration, Section on Certificates of Occupancy

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.