EstatePass
Contract AdminPreconstructioneasy27% of exam part

A carpenter earns $28 per hour. With payroll taxes, workers compensation, and benefits, the total hourly cost is $42. If the carpenter installs 40 linear feet of trim per hour, what is the labor cost per linear foot?

Correct Answer

B) $1.05

Use the total loaded labor cost of $42 per hour divided by 40 linear feet per hour = $1.05 per linear foot. The loaded rate includes all employment costs, not just the base wage.

Answer Options
A
$0.70
B
$1.05
C
$1.68
D
$1.40

Why This Is the Correct Answer

The correct answer is B ($1.05) because we must use the total loaded labor cost, not just the base wage. The loaded cost of $42 per hour includes all employment expenses like payroll taxes, workers compensation, and benefits. Dividing this total cost ($42) by the productivity rate (40 linear feet per hour) gives us the true labor cost per linear foot of $1.05.

Why the Other Options Are Wrong

Option A: $0.70

This answer uses an incorrect calculation method and doesn't properly relate the given loaded rate to the productivity measurement.

Option C: $1.68

This answer appears to double the base wage rate calculation ($28 Γ· 40 = $0.70 Γ— 2 = $1.40), which is not the correct method for calculating loaded labor costs.

Memory Technique

Remember 'LOAD before you DIVIDE' - always use the LOADed labor rate (total cost including benefits) before DIVIDing by productivity to get unit costs.

Reference Hint

Construction estimating chapters covering labor burden rates and unit cost calculations

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.