EstatePass
epa-608-type-2Recovery & Evacuationmedium

The evacuation table splits several of its rows into a column for equipment built before November 15, 1993 and a column for equipment built on or after that date. Which piece of equipment's build date decides which column a technician reads?

Correct Answer

C) The date the recovery or recycling equipment was manufactured

The November 15, 1993 split describes recovery and recycling machines, not appliances. Machines built on or after that date had to meet tougher performance standards, so the table holds them to deeper levels. A brand new rooftop unit worked with a 1990 machine is held to the older column, and a nineteen eighties chiller worked with a modern machine is held to the newer one. Reading the date off the appliance instead of the machine reverses the answer on most large jobs.

Answer Options
A
The date the appliance being serviced was manufactured
B
The date the appliance was last charged with refrigerant
C
The date the recovery or recycling equipment was manufactured
D
The date the technician's certification was originally issued

Why This Is the Correct Answer

The two columns exist because equipment standards changed. Recovery and recycling equipment manufactured on or after November 15, 1993 had to be certified against a tougher standard, and the evacuation table asks those machines to reach deeper levels. The technician therefore looks at the date plate on the recovery machine to choose the column, and at the appliance only to choose the row.

Why the Other Options Are Wrong

Option A: The date the appliance being serviced was manufactured

This reverses the rule. The appliance's own age has no bearing on the required level; only its refrigerant and its normal charge place it on a row.

Option B: The date the appliance was last charged with refrigerant

When an appliance was last charged says nothing about which standard applies. No line of the evacuation table turns on service history.

Option D: The date the technician's certification was originally issued

Certification date affects nothing about evacuation levels. A technician certified last month and one certified in 1994 read the same table the same way.

Memory Technique

The machine picks the column, the appliance picks the row. Two plates, two jobs.

Reference Hint

The November 15, 1993 split in the evacuation table refers to the build date of the recovery or recycling equipment.

Was this explanation helpful?

More epa-608-type-2 Questions

A walk-in cooler condensing unit holds a full charge of twenty-five pounds of R-404A, which is below the fifty pound threshold that brings an appliance under the leak repair provisions. What still applies to this unit?

An office building has thirty water source heat pumps on a common water loop, and each one left the factory assembled, hermetically sealed and charged with four pounds of R-410A. How is one of those units classified?

A data sheet for an unfamiliar refrigerant lists a boiling point of about fifty-five degrees Fahrenheit at atmospheric pressure. What does that tell a technician holding Core and Type II certification?

A technician holds Core, Type I and Type III certification and is sent to recover the charge from a twenty ton rooftop unit charged with R-410A. What does that combination of sections allow on this job?

A fleet garage technician holds only the vehicle air conditioning certification issued under Section 609 and is asked to recover the charge from the shop's own rooftop air conditioner. What does that credential allow?

A split system's outdoor unit, indoor coil and the line set the installer ran and brazed between them are being considered. For the purposes of the refrigerant rules, what makes up the appliance here?

On a new installation the line set is brazed to a factory charged outdoor unit and an indoor coil shipped under a nitrogen holding charge, with the outdoor unit's service valves still closed. What does the recovery requirement call for before that brazing?

A rooftop unit's data plate has weathered until the charge figure cannot be read, and the technician needs the full charge to place the appliance under the evacuation and leak provisions. Where should that figure come from?

A computer room air conditioning unit holds forty pounds of R-407C and connects to a remote air cooled condenser through refrigerant piping run and brazed by the installer. How is that unit classified?

A shop's office manager, who holds no technician certification, is sent to a supply house to pick up a new recovery machine for the commercial crew. What does the sales restriction require at that counter?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.