A completion event occurs on day 40, and undisputed retention must be released within 60 days. What is the outside day for release in this study problem?

Correct Answer

C) Day 100.

Adding 60 days to day 40 gives day 100.

Answer Options
A
Day 60.
B
Day 90.
C
Day 100.
D
Day 120.

Why This Is the Correct Answer

Adding 60 days to day 40 gives day 100.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.