A wage determination lists one locality rate, but the work is performed in another county. What should the contractor check?

Correct Answer

B) Use the rate applicable to the locality where work is performed.

Prevailing wage rates are tied to the craft, classification, and locality for the work performed.

Answer Options
A
Use the lowest county listed in any prior job.
B
Use the rate applicable to the locality where work is performed.
C
Use the worker's home county rate.
D
Use the private shop rate if it is easier.

Why This Is the Correct Answer

Prevailing wage rates are tied to the craft, classification, and locality for the work performed.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.