The bathroom addition progress billing file starts with a $34,600 signed contract and a $3,900 written change order. At 40 percent complete with $4,750 already paid, what additional payment brings billing to the current work value?

Correct Answer

A) $10,650.

The adjusted contract is $38,500. Forty percent complete is $15,400. After the $4,750 already paid, the additional amount is $10,650.

Answer Options
A
$10,650.
B
$8,970 amount.
C
$15,400 amount.
D
$20,150 amount.

Why This Is the Correct Answer

The adjusted contract is $38,500. Forty percent complete is $15,400. After the $4,750 already paid, the additional amount is $10,650.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.