A supplier has not yet received the final check but is asked to sign an unconditional final waiver. What status should be avoided?

Correct Answer

D) False unconditional.

A release should not falsely state unconditional payment status before the payment condition is satisfied.

Answer Options
A
Front-loaded payment.
B
Get approval.
C
Give copy now.
D
False unconditional.

Why This Is the Correct Answer

A release should not falsely state unconditional payment status before the payment condition is satisfied.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.