A drawing calls for painted gypsum board, but the finish schedule calls for tile at the same wall. What is the best pre-bid action?

Correct Answer

D) Request clarification and price the issued answer or addendum.

Document conflicts should be clarified through the bid process so the controlling answer can be priced.

Answer Options
A
Assume the cheaper finish and stay silent.
B
Owner selection deadline.
C
Submit two hidden prices and decide after award.
D
Request clarification and price the issued answer or addendum.

Why This Is the Correct Answer

Document conflicts should be clarified through the bid process so the controlling answer can be priced.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.