Which written-contract detail most directly helps an owner track lien exposure during progress payments?

Correct Answer

B) A payment schedule with phase timing and identification of subcontractors, laborers, and material suppliers.

CSLB mechanics lien guidance says the written contract should include a payment schedule for phases and identify subcontractors/laborers and material suppliers.

Answer Options
A
A list of the contractor's past projects in nearby cities.
B
A payment schedule with phase timing and identification of subcontractors, laborers, and material suppliers.
C
A statement that all invoices will be rounded to the nearest hundred dollars, instead of listing project phases or potential claimants.
D
A clause saying preliminary notices should be ignored until final inspection.

Why This Is the Correct Answer

CSLB mechanics lien guidance says the written contract should include a payment schedule for phases and identify subcontractors/laborers and material suppliers.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.